To serve demand for arbitration of the right to record construction lien on a residential project |
Within 10 days of lodging the NUB for record |
N.J.S.A. 2A:44A- ยง 21b(3) |
To answer a demand for arbitration under American Arbitration Association Construction Industry Rules |
Within 15 calendar days after confirmation of notice of filing of the demand is sent by the AAA |
American Arbitration Association Construction Industry Rules R 4(b), Regular Track Procedures |
To sue to foreclose on a construction lien (following owner demand to commence action) |
Within 30 days following receipt of written notice, by personal service or certified mail, return receipt requested, from the owner requiring the claimant to commence an action to establish the lien claim. |
N.J.S.A. 2A:44A 14 a.(2) |
To answer a summons and civil complaint in NJ Superior Court, Law Division |
Within 35 days after service of the summons and complaint |
Rules 4:6 1(a) and 6:3 1, N.J. Court Rules, 1969 |
To sue to enforce a municipal mechanics lien |
Within 60 days after the project is completed or accepted by resolution of the public agency / project owner |
N.J.S.A. 2A:44 138 |
To file a municipal mechanics lien |
Within 60 days after all work performed by contractor is either complete or accepted |
N.J.S.A. 2A:44 132 |
To lodge for record and serve a notice of unpaid balance (NUB) on a residential project |
No later than 60 days after last date of actual work or delivery of materials or equipment to the project |
N.J.S.A. 2A:44A-6 |
To lodge a construction lien for record on a commercial project |
No later than 90 days after last date of actual work or delivery of materials or equipment to the project |
N.J.S.A. 2A:44A-6 |
To sue to enforce a claim against a surety on contractor's payment bond (public projects only) |
Not before the expiration of 90 days after provision to the sureties and the contractor of the claim statement of the amount due, and not later than one year from the last date of the claimant's actual work or delivery of materials to the project |
N.J.S.A. 2A:44 145 |
To give notice to a surety of a claim against a contractor's payment bond (public projects only) |
Within one year from the last date of the claimant's actual work or delivery of materials to the project |
N.J.S.A. 2A:44 145 |
To sue to foreclose on a construction lien (no owner demand to commence action) |
Within one year of the date of the last provision of work, services, material or equipment, payment for which the lien claim was filed |
N.J.S.A. 2A:44A 14 a.(1) |